15/00607/FULPP | Construction of building to house an electricity substation. | Substation Building Pennefathers Road Aldershot Hampshire
Application Received Date Wed 12 Aug 2015
Application Validated Date Wed 12 Aug 2015
Expiry Date Tue 08 Sep 2015
Actual Committee Date Not Available
Latest Neighbour Consultation Date Not Available
Neighbour Consultation Expiry Date Not Available
Standard Consultation Date Tue 18 Aug 2015
Standard Consultation Expiry Date Tue 08 Sep 2015
Last Advertised In Press Date Fri 21 Aug 2015
Latest Advertisement Expiry Date Not Available
Last Site Notice Posted Date Not Available
Latest Site Notice Expiry Date Not Available
Statutory Expiry Date Wed 07 Oct 2015
Agreed Expiry Date Not Available
Decision Made Date Wed 07 Oct 2015
Decision Issued Date Wed 07 Oct 2015
Permission Expiry Date Sun 07 Oct 2018
Decision Printed Date Not Available
Environmental Impact Assessment Received Not Available
Determination Deadline Wed 07 Oct 2015
Temporary Permission Expiry Date Not Available